Challenges in Public-Private Partnership (PPP) Projects in Malaysia
Abstract
Abstract: The Public-Private Partnership (PPP) implementation approach in Malaysia aims to enhance the delivery of public sector infrastructure and services. However, the Auditor General's Report 2012 highlighted several deficiencies in PPP project management, including delays, poor quality, and inefficient resource use. This study seeks to identify the issues in the management of PPP projects in Malaysia that contribute to these ongoing problems and to propose improvements for enhancing PPP practices. Adopting a qualitative approach with an inductive single case study, the research involved semi-structured interviews with 14 participants conducted over one month in May 2024. The data were analyzed using NVivo Version 14 software through thematic analysis, which generated relevant codes, categories, themes, and domains. The findings reveal seven key strategic issues in PPP project management, such as accountability; incentives and assistance; values, norms, and prevalence; standards and procedures; good and moral governance; duties and roles; and laws and regulations. To improve PPP practices in Malaysia, it is essential for both the government and private sector key players in PPP project management to focus on enhancing capacity building and process optimization. This study provides valuable insights for future PPP project management in Malaysia and serves as a guide for strengthening PPP practices.
Keywords: Public-Private Partnership (PPP); accountability; good governance; key performance index; government sector
References
Ahmad, U., Ibrahim, Y. & Bakar, A. A. (2018). Risk management in the malaysian public private partnership projects. Jurnal Pengurusan, 54,(2018), 101-114.
Alfan, E. (2010). The Malaysian Public-Private Partnership (PPP): Financing the Tolled Highway Projects. Asian Journal of Business and Accounting, 3(2),121-143.
Alireza, V., Mohammadreza, Y., Zin, R. M., Yahaya, N. & Noor, N. M. (2014). An enhanced multi-objective optimization approach for risk allocation in Public–Private Partnership projects: a case study of Malaysia. Journal of Construction Engineering and Management, 41,164-177.
Anantatmula, V. S. (2010). Project manager leadership role in improving project performance. Engineering Management Journal, 22(1), 13-22.
Anuar, R. K. (2012). Malaysia’s BOT method implementation for highway development projects. Tesis Sarjana, Ritsumeikan Asia Pacific University.
Asenova, D., Beck, M., Hardcastle, C. & Chinyio, E. (2010). partnership, value for money and best value in PFI projects: obstacles and opportunities. Public Policy and Administration, 17(5), 5-19.
Asian Development Bank (ADB). (2019). Realizing The Potential Of Public–Private Partnerships to Advance Asia’s Infrastructure Development. Asian Development Bank.
Beh, L.S. (2010). Development and distortion of Malaysian Public-Private Partnerships Patronage, privatised profits and pitfalls. The Australian Journal of Public Administration, 69(S1), 74-84.
Bing Li, Akintoye, A., Edwards, P. & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35.
Casady, C. B. & Baxter, D. (2021). Procuring healthcare public-private partnerships (PPPs) through unsolicited proposals during the COVID-19 pandemic. Journal of Public Procurement, 22(1), 6-16.
Cheung, E., Chan, A. P. C. & Kajewski, S. (2012). Factors contributing to successful public private partnership projects: Comparing Hong Kong with Australia and the United Kingdom. Journal of Facilities Management of Accounting Research, 10(1), 45-58.
Chu Leon Yang, Ying Rong & Huan Zheng. (2020). The strategic benefit of request for proposal/quotation. Journal on Operations Research, 70(3), 1293-1952.
Dhesi, D. (2009). Is Malaysia facing a credit crunch? The Star, 7 Mac: 1.
Ee, O., Halim, H. A. & Ramayah, T. (2013). The effects of partnership quality on business process outsourcing success in Malaysia: key users perspective. Service Business, 7, 227-253.
Fria, R. T. (2005). Successful RFPs in Construction : Managing the Request for Proposal Process. McGraw-Hill.
Greve, C. & Hodge, G. (2011). Transparency in Public-Private Partnerships: Some Lessons from Scandinavia and Australia. Kertas Kerja Persidangan The 1st Global Conference on Transparency Research. Anjuran Copenhagen Business School. Amerika Syarikat, 19-20 Mei.
Hashim, H., Ismail, K. & Che-Ani, A. I. (2017). A polemic on defects liability in Public Private Partnership (PPP) Project. Journal of Engineering Science and Technology, 4 (Special Issue), 219-227.
Hodge, G. (2006). Public private partnerships and legitimacy. UNSW Law Journal, 29(3), 318-327.
Hyun, S., Park, D. & Tian, S. (2019). Determinants of public–private partnerships in infrastructure in emerging economies : Realizing the Potential of Public–Private Partnerships to Advance Asia’s Infrastructure Development. Asian Development Bank.
Ismail, S. & Asuhaimi, F. (2013). Private sector involvement and Public Private Partnership (PPP) in Malaysia. IIUM Press.
Ismail, S. & Harris, F. a.-Z. (2014). Challenges in implementing public private partnership (PPP) in Malaysia. Kertas Kerja Persidangan International Conference on Accounting Studies (ICAS) (2014). Anjuran ICAS. Kuala Lumpur, 18-19 Ogos.
Ismail, S., Mohamad, R. & Said, J. M. (2021). Performance indicators for lifecycle process of Public Private Partnership (PPP) projects in Malaysia. Built Environment Project and Asset Management, 12(5), 704-718.
Izebhor, V. (2022). Should value for money be the sole criteria in opting for ppp option for infrastructure projects?. European Procurement & Public Private Partnership Law Review, 17(1), 23-32.
Jabatan Audit Negara. (2012). Laporan Ketua Audit Negara (2012) Siri 2: Pengurusan Aktiviti Badan Berkanun Persekutuan Dan Pengurusan Syarikat Subsidiari. Jabatan Audit Negara.
Jawatankuasa Siasatan Tadbir Urus Perolehan Dan Kewangan Kerajaan (JKSTUPKK). (2021). Laporan Akhir JKSTUPKK Mengenai Projek Land Swap di bawah Kementerian Pertahanan. Jawatankuasa Siasatan Tadbir Urus Perolehan dan Kewangan Kerajaan.
Jergeas, G., Skulmoski, G. J., Williamson, E. & Thomas, J. L. (2000). Stakeholder management on construction projects. Kertas Kerja Seminar 44th Annual Meeting of American Association of Clinical Endocrinology (AACE) International. Anjuran AACE International. Amerika Syarikat, 27-28 April.
Kaharuddin, S. K., Adnan, H. & Baharuddin, H. E. A. (2021). Identification of successful delivery factors for stakeholder management in Public-Private Partnerships Projects in Malaysia. International Journal of Sustainable Construction Engineering and Technology, 12, 248-257.
Karim, N. A. (2011). Risk Allocation in Public Private Partnership (PPP) project: a review on risk factors. International Journal of Sustainable Construction Engineering & Technology, 2(2), 8-16.
Kementerian Ekonomi (MOE). (2023). Kajian Separuh Penggal Rancangan Malaysia Kedua Belas 2021-2025. Kementerian Ekonomi.
Khadaroo, I. (2005). An institutional theory perspective on the UK's Private Finance Initiative (PFI) accounting standard setting process. Public Management Review, 7(1), 69-94.
Khadaroo, I., Wong, M. S. & Abdullah, A. (2013). Barriers in local e-government partnership: Evidence from Malaysia. Electronic Government an International Journal, 10(1), 19-33.
Khaderi, S. S., Shukor, A. S. A., Bakri, A. S. & Mahbub, R. (2019). Public Infrastructure Project Tendering Through Public Private Partnerships (PPP) – A Literature Review. Kertas Kerja Persidangan MATEC Web of Conferences, IConBEE2018. Anjuran MATEC Web of Conference. Kuala Lumpur, 20 Februari.
Khalifa, N. A., Hmeda, A. a. A., Abidin, R. Z. & Milad, A. (2021). Measuring the characteristics among critical success factors of PPP infrastructure projects Jurnal Kejuruteraan, 33,559-577.
Laureni, A. & Antony, J. (2016). Leadership – a critical success factor for the effective implementation of Lean Six Sigma. Total Quality Management & Business Excellence, 29(5-6), 502-523.
Lee, M., Quising, P., Han, X. & Villaruel, M. L. (2020). Hazard analysis on public-private partnership projects in developing Asia. Journal of Infrastructure Policy and Development, 4(1), 50.
Lou, E., Danuri, M. S. M., Zainon, N. & Rahim, F. M. (2013). Analysis of practices for Private Finance Initiative (PFI) procurement process: Malaysia vs United Kingdom. The Malaysia Surveyor, 48(1),13-20.
Michalski-Karl, R., Pernsteiner, S. & Schaffhauser-Linzatti, M. M. (2009). Signaling Public Private Partnership activities: reporting behavior within annual reports. International Advances in Economic Research, 15(2), 178-185.
Mladenovic, G., Wundsch, B., Vajdic, N. & Salaj, A. T. (2013). Use of key performance indicators for PPP transport projects to meet stakeholders' performance objectives. Built Environment Project and Asset Management, 3(2), 228-249.
Mohamad, R., Ismail, S. & Said, J. M. (2016). Performance objectives of public private partnership implementation in Malaysia: perception of key players. Journal of Asia Business Studies, 12(1), 17-30.
Mohd-Rahim, F. A., Zainon, N. & Loo, S.C. (2017). Project Life Cycle Risk of Public-Private Partnership (PPP) Projects for Construction Sustainability. Journal of Design and Built Environment, Special Issue (1), 39-53.
Musawa, M. S., Ismail, S. & Ahmad, H. (2017). Disclosure of public-private partnership (PPP) voluntary information : Case of Malaysian PPP projects. Asia-Pacific Journal of Business Administration, 9(2), 146-163.
Neely, A., Mills, J., Platts, K., Richards, H., Grocery, M., Bourne, M. & Kennerly, M. (2000). Performance measurement system design: Developing and testing a process-based approach. International Journal of Operations and Production Management, 20(10), 1119-1145.
Nor Azlina Kamarudin. (2013). Value creation in public private partnership: Factors contributing to sustainable performance. [Tesis Dr. Fal, UKM-Graduate School of Business, Universiti Kebangsaan Malaysia].
Ogunsanmi, O. (2013). Stakeholders' perception of key performance indicators (KPIs) of Public-Private Partnership (PPP) projects. International Journal of Construction Supply Chain Management, 3(2), 27-38.
Olander, S. & Landin, A. (2008). A comparative study of factors affecting the external stakeholder management process. Construction Management and Economics, 26(6), 553-561.
Osei-Kyei Robert & Albert P.C. Chan. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346.
Paech, B., Heinrich, R., Zorn-Pauli, G., Jung, A. & Tadjiky, S. (2012). Answering a Request for Proposal – challenges and proposed solutions. B.Regnell and D.Damian Jorunal, 1,16-29.
Palcic, D., Reeves, E. & Siemiatycki, M. (2019). Performance: the missing 'P' in PPP research? Annals of Public and Cooperative Economics, 90(2), 221-226.
Samsudin, N. A., Hashim, H. A., Hamzah, E. & Zainol, N. N. (2022). Evaluation Criteria of Facilities Management Through Public-Private Partnership (PPP) Scheme. International Journal of Sustainable Construction Engineering and Technology, 13(4), 1-7.
Sands, V. (2004). Victoria’s partly-privatised prison system: an accountability report card. Asia Pacific Journal of Public Administration, 26(2), 134-137.
Schepper, S. D., Dooms, M. & Haezendonck, E. (2014). Stakeholder dynamics and responsibilities in Public–Private Partnerships: A mixed experience. International Journal of Project Management, 32(7), 1210-1222.
Shaoul, J., Stafford, A. & Stapleton, P. (2010). Financial black holes. Accounting, Auditing & Accountability Journal, 23(2), 229-255.
Sharma, C. (2012). Determinants of PPP in infrastructure in developing economies. Transforming Government: People, Process and Policy, 6,149-166.
Sharma, C. (2022). Who does it better and why? Empirical analysis of public-private partnership in infrastructure in Asia-Pacific. Property Management, 41(3), 309-335.
Shen, L., Platten, A. & Deng, X. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 26(7), 587-594.
Som, R. M., Ismail, I. A., Omar, Z., Alias, S. N. & Asimiran, S. (2023). An assessment of facilitative leadership, communication quality and trust on Public-Private Partnership success. Journal of Asia Business Studies, 17(5), 1042-1066.
Tang, L. & Shen, Q. (2013). Factors affecting effectiveness and efficiency of analyzing stakeholders' needs at the briefing stage of Public Private Partnership projects. International Journal of Project Management, 31,513-521.
Thomas, A. V., Kalidindi, S. & Ananthanarayanan, K. (2003). Risk perception analysis of BOT road project participants in India. Construction Management and Economics, 21(4), 393-407.
Unit Kerjasama Awam Swasta (UKAS). (2009). Garis Panduan Kerjasama Awam-Swasta.
Unit Perancang Ekonomi (UPE). (2015). Buku Merah UPE, JPM : Langkah-langkah penambahbaikan projek pembangunan Rancangan Malaysia Lima Tahun (RMLT). Unit Perancang Ekonomi.
Vecchi, V., Hellowell, M., Croce, R. D. & Gatti, S. (2017). Government policies to enhance access to credit for infrastructure-based PPPs: an approach to classification and appraisal. Public Money and Management, 37(2),133-140.
Wood-Harper, A. T., Ibrahim, O. & Ithnin, N. (2004). An interconnected success factor approach for service functional in Malaysian electronic government. Kertas Kerja Seminar 6th International Conference on Electronic Commerce (ICEC). Anjuran ICEC. The Netherlands, 25-27 Oktober.
World Bank Group (WBG). (2015). A Framework for Disclosure in Public-Private Partnership Projects. World Bank Group.
World Bank Group (WBG). (2018). Procuring Infrastructure Public-Private Partnerships Report 2018 : Assessing Government Capability to Prepare, Procure and Manage PPPs. World Bank Group.
Yamaguchi, H., Uher, T. E. & Runeson, G. (2001). Risk Allocation in PFI Projects. Kertas Kerja Persidangan 17th Annual ARCOM Conference. Anjuran Association of Researchers in Construction Management. Australia, 2-4 September.
Yuan, J., Wang, C., Skibnieski, M. J. & Li, Q. (2011). Developing Key Performance Indicators for Public-Private Partnership Projects: Questionnaire Survey and Analysis. Journal of Management in Engineering, 28(3), 252-264.
Yuan, Y., Lai, F. & Chu, Z. (2018). Continuous usage intention of internet banking: a commitment‑trust model. Springer-Verlag GmbH Germany, 17,1-25.
Yin, R. K. (2018). Case Study Research and Applications: Design and Methods. Sage Publications.
Zawawi, M. I. Z., Kulatunga, U. & Thayaparan, M. (2016). Malaysian experience with public-private partnership (PPP) : Managing unsolicited proposal. Built Environment Project and Asset Management, 6(5), 508-520.
Zhang, L., Cao, T. & Wang, Y. (2018). The mediation role of leadership styles in integrated project collaboration: An emotional intelligence perspective. International Journal of Project Management, 36(2), 317-330.
Zhang, X. (2005). Critical Success Factors for Public–Private Partnerships in Infrastructure Development. Journal of Construction Engineering and Management, 131(1), 3-14.
Zulch, B. (2014). Leadership Communication in Project Management. Procedia - Social and Behavioral Sciences, 119, 172-181.
Full Text:
PDFDOI: http://dx.doi.org/10.17576/ebangi.2024.2104.23
Refbacks
- There are currently no refbacks.
-
_________________________________________________
eISSN 1823-884x
Faculty of Social Sciences & Humanities
Universiti Kebangsaan Malaysia
43600 UKM Bangi, Selangor Darul Ehsan
MALAYSIA
© Copyright UKM Press, Universiti Kebangsaan Malaysia